Subtasks listed according to due date?
Author Message
uarnold

Posted: Jan 18, 2013
Score: 0 Reference
Hello,

I use subtasks for my projects. Now it is normally the case the the main task has a completion date quite far in the future. But one or several sub tasks have a due date which is quite near.

I very much like the main view, where tasks are sorted according to due date (due in the past, due today, ....)

Unfortunately I did not find out yet, how I can see the subtasks, also when they are due. The main task is listed accordingly, but I miss all the sub tasks which are due today, or the next seven days etc,

Thanks for a hint
Ulrich
Jake

Toodledo Founder
Posted: Jan 18, 2013
Score: 0 Reference
Two ways

1) View your list with subtasks flattened
2) Go into your settings, and under the subtask section you can change how subtasks are displayed in indented mode.