Due between two dates
Author | Message |
---|---|
Wolfgang Enneker |
Good morning,
I have a task which I can not start before a certain date (e.g. 1-Apr-13). Once that day has passed, I have to complete it within 7 days. How can I use Toodledo to track this task? Enter two tasks (one with a complete after date and one with a complete before date)? I know that this may be a rare requirement. Wolfgang |
alexandremrj_2 |
Hello,
you can use the start date field and the due date field. This way you can filter by hiding future tasks (tasks that have a start date in the future) and you have the due date for you task. |
Wolfgang Enneker |
Thank you for your help - this is a good solution.
Wolfgang |