Hello. I have 2 questions.
1 - My week at work are Monday to Friday. In a daily task, I create work Saturday and Sunday too. Can it be avoided?. 2 - Tasks in a row. My Task B can only started when the end of my Task A. How can this indicate? Thanks. Leo |
Jake Toodledo Founder |
1) Select "advanced repeat" and type in "every weekday". http://www.toodledo.com/info/help.php?sel=2
2) This is not currently supported, but it is on our to-do list. You could manually manage this with the status field. |
leonardobergua |
Thanks.
|